Costs / Sizing

Find out how many panels you really need, and what you should pay

Most 4-bed homes land on a 5 to 7 kWp system at £7,600 to £10,800 installed. The bedroom count is not what sets that figure, though. Your annual kWh does, and using the wrong one is how people end up paying for capacity they cannot spend.

Four bedrooms tells an installer roughly how much roof you have and how many people might live under it. It tells them nothing about whether you run an EV, a heat pump, an electric shower or three teenagers with gaming PCs, and those are the variables that decide the size of the system and therefore the size of the bill.

Key points
  1. Budget £7,600 to £9,900 for a 6.2 kWp system fully installed. That is 14 panels at 440W, the size most 4-bed homes settle on. A smaller 5 kWp runs £6,700 to £8,700, a larger 8.8 kWp £10,200 to £13,200. Prices checked August 2026, 0% VAT until 31 March 2027.
  2. Add £5,500 to £7,500 for a 10 kWh battery. That takes the typical 4-bed package to £13,000 to £17,500. Battery capacity itself benchmarks at roughly £450 to £650 per kWh installed, which is the number to compare quotes on.
  3. Size from your annual kWh, not your bedroom count. Take last year’s electricity usage off your bill, divide by about 950, and that is the kWp your roof needs to match it. A 4-bed on gas heating with no EV typically uses 3,500 to 4,200 kWh.
  4. Bigger systems cost less per kWp but self-consume a smaller share. A 6.2 kWp array costs about £1,350 per kWp against £1,530 for a 4 kWp, so the marginal panels are cheap. They also generate units you may end up selling at 12p rather than saving at 26.32p.
  5. Most 4-bed systems cross the 3.68 kW grid threshold. That means either a G99 application taking up to 45 working days, or an export-limited inverter. Ask which your quote assumes, because it changes the install date.

What a 4-bed house actually pays in 2026

£7,600 to £9,900 fully installed for the 6.2 kWp system most 4-bed homes end up with, as at August 2026. That is 14 panels at 440W each, an inverter, mounting, scaffolding, electrical work, DNO paperwork and MCS certification, with VAT at 0%.

The range exists because two 4-bed houses can be very different jobs. A 1970s detached with a clear 40 m² rear roof and a driveway to park the scaffold on sits at the bottom. A three-storey Victorian townhouse with a hipped roof, a party wall and no vehicle access sits at the top, on the same kit.

Installed cost by system size, UK, August 2026
System sizePanelsInstalled costCost per kWp
4.0 kWp10£5,800 to £7,600~£1,530
5.0 kWp12£6,700 to £8,700~£1,420
6.2 kWp14£7,600 to £9,900~£1,350
7.0 kWp16£8,300 to £10,800~£1,300
8.8 kWp20£10,200 to £13,200~£1,290
10.0 kWp23£12,000 to £15,600~£1,330

Read the right-hand column rather than the middle one. Cost per kWp falls steadily up to about 8 kWp and then starts climbing again, because a system that size usually needs a three-phase supply check, a full G99 application and sometimes a second inverter. The cheapest capacity you will ever buy is the panels added to a system that already has its scaffold up and its inverter paid for.

£8,360 Typical 6.2 kWp 4-bed install
3,900 kWh/yr, gas-heated 4-bed
34 m² Roof area for 14 panels
9 yrs Typical payback, no battery
Terms used in this guide
kWp
Kilowatt peak, the rated output of the array under standard test conditions. It is a capacity figure, not a generation figure. Fourteen 440W panels give you 6.16 kWp.
Kk value
The MCS figure for annual kWh per kWp at your postcode, pitch and orientation. Multiply by your kWp to get the annual estimate. Around 950 in the Midlands on a south-facing roof.
Self-consumption
The share of generation you use in the house rather than export. It is the single biggest driver of return, because a self-consumed unit is worth 26.32p and an exported unit is worth about 12p.
SEG
Smart Export Guarantee. Suppliers set their own export rates, so the market spread runs from about 3p to 15p per kWh for households on an independent install.
G98 and G99
Grid connection standards. G98 covers inverters up to 3.68 kW on a single phase and is notified after the fact. G99 is applied for in advance and can take up to 45 working days.
Export limiting
Configuring a larger inverter so it never pushes more than a set figure to the grid, usually 3.68 kW. It keeps a bigger system inside the simpler notification route.

Bedrooms are the wrong input, and everyone uses them anyway

Your annual electricity consumption sets your system size. Bedroom count is a proxy for roof area and household size, and it correlates with consumption loosely enough to be worth checking rather than assuming.

Here is the method, and it takes about two minutes. Find the annual kWh figure on your electricity bill or in your supplier’s app. Divide it by 950 if you are in England or Wales on a roughly south-facing roof, or by 850 in Scotland or on an east or west slope. That gives you the kWp needed to generate as much as you use across a year. Divide that by your panel wattage in kW, so 0.44 for a 440W panel, and you have the panel count.

Worked through: a 4-bed using 3,900 kWh a year in the Midlands needs 3,900 divided by 950, which is 4.1 kWp, which is 10 panels. That is smaller than the 14 panels most quotes propose. The gap between those two numbers is worth understanding before you sign anything, and the rest of this guide is largely about it.

Annual electricity use, 4-bed house, by what is in it
HouseholdAnnual kWhMatching kWp
Gas heating, both adults out weekdays2,900 to 3,4003.1 to 3.6
Gas heating, family of four, some home working3,600 to 4,2003.8 to 4.4
As above plus one EV at 8,000 miles a year5,900 to 6,6006.2 to 6.9
Gas heating, EV, hot tub or electric shower use7,000 to 8,5007.4 to 8.9
Air source heat pump, no EV7,500 to 10,0007.9 to 10.5
Heat pump plus EV, all-electric home10,000 to 13,00010.5 to 13.7

The pattern in that table is the whole sizing question. Two 4-bed houses on the same street can sit at 3,000 kWh and 11,000 kWh, a difference of nearly four to one, and the bedroom count is identical in both. An EV adds roughly 2,500 kWh a year at typical mileage. A heat pump adds 4,000 to 6,000. Neither is visible from the kerb.

Tip

If you are planning an EV or a heat pump within the next five years, size the array for it now rather than adding panels later. Retrofitting six panels to an existing system means a fresh scaffold at £550 to £950, a possible inverter swap, and a new DNO application. Doing it at the outset costs the panels and the rails, roughly £200 to £320 each.

Where the money goes, line by line

Panels are about a quarter of your bill. Labour and scaffolding together are more than a third. That ratio surprises most people, and it explains why quotes for identical hardware come back hundreds of pounds apart.

6.2 kWp on a 4-bed detached, no battery, Midlands Total £8,360
Solar panels, 14 x 440W
Tier-1 N-type mono, 25-year product warranty
£2,030
Hybrid inverter, 5 kW
Battery-ready, export limitable, 10 to 12 year warranty
£1,250
Mounting system
Rails, hooks, flashings, bird mesh, two roof slopes
£780
Electrical works
DC and AC cabling, isolators, surge protection, CT clamp, generation meter
£550
Scaffolding
Two elevations, 2-week hire, 2-storey detached
£950
Labour
2.5 days, team of 3, MCS-certified contractor
£2,250
Application and certification
G99 application, MCS certificate, commissioning, handover pack
£550
Total installed, 0% VAT until 31 March 2027
£8,360

Two lines move most between quotes. Scaffolding on a 4-bed detached with two elevations runs £850 to £1,200, against £450 to £650 for a single-elevation job on a semi, and some firms fold it into the headline while others itemise it. Labour rates in London and the South East run 20% to 35% above Yorkshire or the North East for the same two and a half days of work.

Heads up

The 0% VAT rate on qualifying residential solar and battery installations ends on 31 March 2027 and reverts to 5%. On an £8,360 install that final window is worth about £418. On a £14,500 package with a battery it is worth about £725. Useful to know when you are deciding between this financial year and next, and not a reason to sign on the doorstep.

Cost per kWp is the only number that compares quotes fairly

Divide the total by the kWp and you get a figure you can hold against any other quote regardless of system size. In 2026 UK domestic solar sits at roughly £1,250 to £1,700 per kWp, and where you land inside that band tells you more than the headline total does.

Installed cost per kWp by system size, UK, 2026
3.0 kWp (7 panels) £1,680
4.0 kWp (10 panels) £1,530
5.0 kWp (12 panels) £1,420
6.2 kWp (14 panels) £1,350
8.8 kWp (20 panels) £1,290
10.0 kWp (23 panels) £1,330

The curve bottoms out around 8 kWp and turns back up. Below that point you are spreading a fixed scaffold, a fixed inverter and a fixed set of paperwork across fewer panels. Above it you start paying for extra complexity: a larger or second inverter, a three-phase check, and in some cases a network reinforcement conversation with the DNO.

That makes the 6 to 8 kWp band the best value per unit of capacity for a 4-bed, and it is one reason quotes cluster there. Whether you should buy capacity at its cheapest is a different question, answered under the self-consumption ceiling further down.

Did you know

The marginal cost of an extra panel on a job already going ahead is roughly £200 to £320 fitted, against an average of £1,350 per kWp across the whole system. At 440W that marginal panel costs £455 to £730 per kWp of added capacity, less than half the system average. If the roof space and the inverter headroom exist, panels 11 through 14 are the cheapest capacity in the entire quote.

What your region does to the price

The same 6.2 kWp system costs about £2,500 more in London than in the North East. Almost all of that gap is labour and scaffolding rather than hardware, which is priced nationally.

6.2 kWp installed cost by region, indicative, August 2026
RegionTypical installedAgainst UK average
North East£7,350-12%
Scotland£7,500-10%
Yorkshire and the Humber£7,700-8%
North West£7,860-6%
Wales£7,860-6%
Midlands£8,360UK average
South West£8,530+2%
East of England£8,860+6%
South East£9,530+14%
London£9,870+18%

There is a compensation buried in that table. The regions paying most are the regions generating most: a 6.2 kWp array in the South East produces roughly 6,200 kWh a year against 5,300 kWh in Scotland. The higher price buys more output, so payback periods across the UK are closer together than either the cost table or the yield table suggests on its own.

Worth knowing

Regional figures are averages of very different jobs, so treat them as a sense check rather than a target. What they are good for is spotting an outlier. If you are in Yorkshire and holding a £12,000 quote for 6.2 kWp with no battery, you are 55% above your regional average and something in that quote needs explaining.

What a battery adds, and what it is actually worth

£5,500 to £7,500 for 10 kWh installed alongside the panels, which takes a typical 4-bed package to £13,900 to £17,400. Fitted at the same time as the solar it is £600 to £900 cheaper than retrofitting later, because you use one hybrid inverter and one visit instead of two.

Compare battery quotes on cost per kWh, not on the total. The installed benchmark in August 2026 is roughly £450 to £650 per usable kWh for a mainstream LiFePO4 unit. A 10 kWh battery quoted at £8,500 is £850 per kWh, which needs a reason attached to it: backup power capability, a longer warranty, or a modular design you intend to expand.

Battery sizing against a 4-bed load, installed cost August 2026
CapacityInstalled costPer kWhFits which household
5 kWh£3,000 to £4,500£600 to £900Gas heating, no EV, evening use only
10 kWh£5,500 to £7,500£550 to £750The default for a 4-bed with 3,500 to 6,000 kWh a year
15 kWh£7,800 to £10,200£520 to £680EV charging at home, or a heat pump
20 kWh£9,800 to £13,000£490 to £650All-electric home above 9,000 kWh a year

Note that per-kWh cost falls as capacity rises, for the same reason panel cost per kWp does: the inverter, the wiring and the labour are largely fixed. If you are already buying 10 kWh, the step to 15 kWh costs roughly £2,300 for 5 kWh, which is £460 per kWh, better than the average price of the first 10.

Storing your own solar does not pay for a battery in the UK in 2026. Buying overnight electricity at 7p to 9p and displacing daytime units at 26.32p does. Size the battery around your overnight charging window, not around your solar surplus. Solar Love analysis // August 2026

The payback arithmetic, one number at a time

Nine years for panels alone on a typical 4-bed. Here is the construction, because the construction is where quotes get misread.

Take the 6.2 kWp array above at £8,360, on a south-west facing Midlands roof with a Kk of 900. That generates 5,580 kWh a year. The household uses 3,900 kWh across the year, and without storage it manages 32% self-consumption because the array peaks at midday and the house is busiest at 7am and 6pm. That is 1,786 kWh used at home. At the October 2026 cap rate of 26.32p, those units are worth £470. The remaining 3,794 kWh is exported at 12p, worth £455. Year one total: £925. Divide £8,360 by £925 and you get 9.0 years.

Look at which base each rate was applied to. Two thirds of your generation earned the low number. That is what a battery buys back.

So run it again with a 10 kWh battery at £6,200, taking the package to £14,560. Self-consumption rises to 63% of generation, which is 3,515 kWh at 26.32p, worth £925. Export drops to 2,065 kWh at 12p, worth £248. Year one total: £1,173. That is £248 more than the panels produced alone, against £6,200 of hardware, so the battery repays in 25 years on solar storage alone. Its warranty is 10 to 12 years.

Now add the part that makes it work. On a smart tariff with overnight rates in the 7p to 9p band through mid-2026, charging 8 kWh overnight at 8p costs 64p and displaces 8 kWh of daytime import at 26.32p worth £2.11. That is £1.47 banked per cycle. Run it 250 nights a year, mostly in the months when solar cannot fill the battery, and it is £368. Total annual value climbs to £1,541, and the whole £14,560 package pays back in 9.4 years.

Panels only
£925

Year one value on £8,360. 32% self-consumed at 26.32p, 68% exported at 12p. Payback 9.0 years.

Panels + 10 kWh + smart tariff
£1,541

Year one value on £14,560, including £368 of overnight arbitrage. Payback 9.4 years.

The two payback figures land within five months of each other, which is the honest answer to whether a 4-bed should add a battery. It does not shorten your payback. It roughly doubles the annual return on a package that costs roughly 75% more, and it gives you backup capability and a hedge against export rates falling again.

Warning

Treat any payback figure with no date on the export rate as unusable. Outgoing Octopus dropped from 15p to 12p on 1 March 2026, its first change since September 2022. On a 6.2 kWp array exporting 3,794 kWh, that single change cut annual income by £114 and pushed payback out by roughly 13 months. Ask which rate the projection assumes and when it was last verified.

The self-consumption ceiling nobody mentions

You cannot use more electricity than you use. It sounds obvious written down, and it is the single most common flaw in solar quotes for larger houses.

The 4-bed in the example above uses 3,900 kWh a year and generates 5,580 kWh from a 6.2 kWp array. Even with a perfect battery, perfect timing and no losses, the most it could ever self-consume is 3,900 kWh, which is 70% of generation. In practice the ceiling is lower, around 60% to 65%, because generation and demand are seasonally mismatched: the array produces most in June when the house needs least, and least in December when it needs most.

The consequence is that a large array on a modest load has a hard limit on how good it can get, and every kWp added past that limit produces units that can only ever be exported at 12p. The saving stops improving. The export income keeps rising, but at less than half the value.

Same 4-bed at 3,900 kWh a year, with a 10 kWh battery, by array size
ArrayGenerationSelf-consumedAnnual valueValue per extra kWp
4.0 kWp3,600 kWh2,700 kWh (75%)£819baseline
5.0 kWp4,500 kWh3,105 kWh (69%)£985£166
6.2 kWp5,580 kWh3,515 kWh (63%)£1,173£157
8.8 kWp7,920 kWh3,700 kWh (47%)£1,480£118
10.0 kWp9,000 kWh3,750 kWh (42%)£1,617£114

Track the right-hand column. Each extra kWp is worth less than the one before it, while costing roughly the same to install. Past about 6 kWp on a 3,900 kWh household the additional capacity is effectively a small export business rather than a bill reduction. That is not automatically bad, but it is a different investment with a different return, and it should be priced as one.

The fix is not a smaller array. It is a bigger load. If you are adding an EV or a heat pump, the ceiling rises with your consumption and the large array becomes the correct call. If your consumption is fixed at 3,900 kWh and staying there, stop at 5 to 6 kWp and put the difference towards the battery.

6.2 kWp + 10 kWh on a 4-bed
3.7 / 5
Annual bill reduction
4.5
Grid independence
4.2
Payback against 25-year life
4.0
Value per pound spent
3.8
Headroom to add an EV later
4.1
Self-consumption headroom
3.4
Upfront affordability
2.6

Most 4-bed systems cross the 3.68 kW grid threshold

Anything above a 3.68 kW inverter on a single-phase supply needs G99 approval from your distribution network operator before installation, and that takes up to 45 working days. Below it, a G98 notification goes in after commissioning with no waiting. Around 95% of UK homes are single phase, and almost every 4-bed system is above the line.

There are two ways through, and your quote should say which one it uses. The first is a full G99 application, which allows the inverter to export at its full rating and adds four to nine weeks to the timeline. The second is export limiting: fitting a 5 kW or 6 kW inverter configured never to push more than 3.68 kW to the grid, which keeps the job inside the simpler route.

Export limiting costs you very little in practice. On a 6.2 kWp array the curtailed energy is typically 2% to 4% of annual generation, concentrated in perhaps 80 hours across April to July when the array is at full output and the house is drawing almost nothing. On 5,580 kWh that is 110 to 220 kWh, worth £13 to £26 a year at the 12p export rate it would have earned. Set against a nine-week delay, most households take the limit.

Worth knowing

Batteries change this calculation in your favour. An export-limited system with storage curtails almost nothing, because the surplus that would have been clipped goes into the battery instead of being thrown away. If you are fitting both at once, export limiting costs you close to nothing and saves you the G99 wait entirely.

One trap on retrofits: adding an AC-coupled battery with its own 5 kW inverter to an existing G98-registered solar system pushes combined site capacity over the threshold and triggers a fresh G99 application on a system that was previously compliant. If a battery is on the horizon, specify the hybrid inverter at the first install.

Why two quotes for the same house differ by £4,000

Sales cost, mostly. Not hardware, not labour hours, not roof complexity. The largest single variable in UK domestic solar quoting is how the company found you.

National sales-led firms that generate leads through door-knocking, cold calling or paid comparison placements carry an acquisition cost per sale that has to sit somewhere in the price. Local MCS-certified installers working on referral and repeat trade do not carry it. The same 6.2 kWp specification routinely comes back at £8,000 from a regional installer and £12,000 to £13,000 from a national operating a commissioned sales team, and the panels in both vans are frequently from the same distributor.

Get three quotes, and make sure at least two of them are from installers based within 30 miles of the property. If all three come through the same comparison form, you have three quotes from the same acquisition channel and you have not tested the market at all. Standard advice among MCS contractors

Beyond acquisition cost, four things legitimately move a quote. Roof covering: slate and clay tiles take longer to work and cost £300 to £700 more than concrete tiles. Access: no driveway or a rear garden with no side gate adds scaffold hire and handling time. Hipped roofs: more cuts, more rails, fewer panels per square metre. Consumer unit condition: an old board without RCD protection needs upgrading before an installer will connect, at £400 to £900.

Do

Ask every quote for its cost per kWp, and for the battery cost per kWh separately from the panels.

Get one quote from an installer you found yourself, outside any comparison form.

Check the MCS certification number on the MCS website rather than taking the logo on the letterhead as evidence.

Don’t

Sign at the first appointment. A discount that expires when the salesperson leaves your kitchen was never a discount.

Pay more than 25% as a deposit. Above that you are outside the usual deposit protection threshold.

Accept a generation estimate that does not name your postcode zone and Kk value.

What the quote must show

  • Cost per kWp, and battery cost per kWh, calculated separately. If the quote is a single package price with no breakdown, ask for one before comparing it against anything.
  • Panel make, model and wattage, plus count. “14 x tier-1 440W” is not a specification. You need the model number to read the datasheet.
  • Inverter model, rating, and whether it is export limited. If limited, at what value and whether the limit is a software setting you can change after a future G99.
  • G98 or G99, stated explicitly, with the expected timeline. A G99 job should show the 45 working day window in the schedule, not in the small print.
  • Your MCS postcode zone and the Kk value used. Plus the shade factor from the sun-path assessment as a number between 0 and 1.
  • Scaffolding as a separate line with the hire period. This is the most commonly hidden cost on a 4-bed and it varies by £400 between quotes for the same house.
  • Three warranties, stated separately. Panel product warranty, inverter warranty and workmanship warranty run for three different periods.
  • Whether the consumer unit needs upgrading, priced. Finding this out on install day is how a fixed price becomes a variable one.

Three real 4-bed households, costed

The same house, three different loads. All figures are Midlands, south-west facing roof, Kk 900, August 2026 pricing, 26.32p import and 12p export.

Empty weekdays
Gas heating, no EV
£6,300
Consumption
3,100 kWh/yr
System
4.4 kWp, no battery
Annual value
£714
Payback
8.8 years
Grid route
G98 notification
Family plus one EV
Gas heating, 8,000 mi/yr
£14,560
Consumption
6,300 kWh/yr
System
6.2 kWp + 10 kWh
Annual value
£1,541
Payback
9.4 years
Grid route
Export limited to 3.68 kW
All-electric
Heat pump plus EV
£19,800
Consumption
11,000 kWh/yr
System
8.8 kWp + 15 kWh
Annual value
£2,308
Payback
8.6 years
Grid route
Full G99 application

The right-hand column has the shortest payback of the three, which is the opposite of what most people expect from the most expensive package. It works because an all-electric home has enough load to absorb almost everything the array makes, so a far larger share of generation earns 26.32p instead of 12p. The middle column carries the tag because it fits the largest number of 4-bed households, not because it returns the most.

The left-hand column is the useful comparison. It costs less than half the middle one and pays back marginally faster. If your consumption is really under 3,200 kWh and staying there, a modest array with no battery is a defensible choice that most quotes will not offer you.

When to spend less than the quote in front of you

Four situations where the right decision is a smaller system, a delay, or nothing at all. A good installer will raise these unprompted, and whether they do is a reasonable test of the firm.

Spend the full amount when
  • You run or are about to run an EV, a heat pump or both
  • Someone is home during weekdays
  • You intend to stay in the house more than eight years
  • The roof covering has 15 years or more of life left
  • You have the roof area for 14 or more panels without shading
Spend less, or wait, when
  • Annual use is under 3,000 kWh and not rising
  • The roof is due for re-covering within ten years
  • You are likely to move within five years
  • The array would sit mostly on a shaded or north-facing slope
  • The quote is a finance agreement you have not read the APR on

The roof condition case is the cheapest to avoid and the most expensive to ignore. Removing and refitting a 6.2 kWp array so a roofer can strip and re-cover costs £1,300 to £2,200, plus a second scaffold. If the covering has under a decade left, do the roof first and fit the panels onto the new one.

The moving case is often overstated but worth being honest about. Owned panels with an MCS certificate and a transferable SEG registration are a mild positive at valuation, typically adding less than the install cost. If you are moving inside five years you will not have recovered the outlay through savings either, so the money is better spent elsewhere.

Important

Check whether a quote is a cash price or a finance price. Solar sold on a credit agreement at 9.9% to 14.9% APR over ten years can add £3,500 or more to a £14,000 package, and the payback figure in the brochure will almost never include the interest. Ask for the total amount payable, not the monthly payment.

Frequently asked

4-bed solar costs, answered
How much do solar panels cost for a 4-bedroom house in the UK?

£7,600 to £9,900 fully installed for a 6.2 kWp system of 14 panels, which is the size most 4-bed homes settle on, as at August 2026. Smaller 5 kWp systems run £6,700 to £8,700 and larger 8.8 kWp systems £10,200 to £13,200. Adding a 10 kWh battery takes the package to £13,900 to £17,400. VAT is 0% until 31 March 2027.

How many solar panels does a 4-bed house need?

Usually 12 to 16 panels at 440W, which is 5.3 to 7.0 kWp. Size it from your bill rather than the bedroom count: divide your annual kWh by 950 to get the kWp needed, then divide by 0.44 for the panel count. A 4-bed on gas heating with no EV typically uses 3,500 to 4,200 kWh a year and needs around 10 panels to match that.

How much roof space do I need for a 4-bed system?

About 34 m² for 14 panels, allowing 300mm clearance at eaves, ridge and verges. Each 440W panel is roughly 1.95m by 1.13m, so 2.2 m². A typical 4-bed rear roof slope of 8m by 4.5m takes 14 to 16 panels comfortably if it is clear of chimneys and dormers.

How much will solar panels save a 4-bed house per year?

Around £925 a year for a 6.2 kWp array with no battery, split roughly £470 in bill savings and £455 in export income. With a 10 kWh battery and a smart tariff the combined figure reaches about £1,541. Calculated on the October 2026 cap rate of 26.32p per kWh and a 12p export rate.

What is the payback period on solar for a 4-bed house?

Nine years for panels alone on a typical Midlands 4-bed, and 9.4 years for panels plus a 10 kWh battery on a smart tariff. Southern England runs a year or so shorter, Scotland a year or so longer. Adding a battery does not shorten the payback, it roughly doubles the annual return on a package costing about 75% more.

Is a 6kW solar system enough for a 4-bed house?

More than enough for a gas-heated 4-bed with no EV, and about right for one with a single EV. A 6.2 kWp array generates roughly 5,600 kWh a year in the Midlands, against typical consumption of 3,500 to 4,200 kWh. If you have a heat pump, look at 8 to 10 kWp instead.

Do I need planning permission for solar panels on a 4-bed house?

Usually no. Roof-mounted solar in England is permitted development provided panels project no more than 200mm from the roof plane and sit below the highest point of the roof. Listed buildings need listed building consent, and in conservation areas, AONBs and National Parks a slope fronting a highway needs a full application. Wales, Scotland and Northern Ireland run their own rules.

Why is one quote £8,000 and another £12,000 for the same system?

Almost always sales acquisition cost. National firms using commissioned salespeople or paid lead generation carry an acquisition cost per sale that sits inside the price. Local MCS installers working on referral do not. Compare on cost per kWp, and make sure at least one of your three quotes came from an installer you found yourself rather than through a comparison form.

Will solar panels add value to a 4-bed house?

Owned panels with an MCS certificate and a transferable SEG registration are a mild positive at valuation, and they improve the EPC rating, which matters more on larger properties. The uplift is generally less than the install cost, so treat resale value as a secondary benefit rather than part of the payback calculation. Leased or rent-a-roof panels are a different matter and can complicate a sale.

Bottom line

Price the load, not the house

A 4-bed house will be quoted somewhere between £7,600 and £9,900 for the 6.2 kWp system that has become the default, and between £13,900 and £17,400 with a 10 kWh battery. Those are fair numbers at August 2026 prices, and anything materially above them needs a reason attached.

What decides whether the money works is your annual kWh, not your bedroom count. At 3,000 kWh a year a 4 kWp array with no battery is the right answer and will pay back faster than anything larger. At 11,000 kWh with a heat pump and an EV, an 8.8 kWp array with 15 kWh of storage pays back faster still, because there is enough load to absorb it. The worst outcome is a large array on a small load, where every extra kWp earns 12p instead of 26.32p.

Take last year’s kWh figure off your bill before you speak to anyone. Divide it by 950. Then get three quotes, at least two from installers based within 30 miles, and compare them on cost per kWp and cost per kWh of battery rather than on the headline total.

METHODOLOGY: Installed pricing verified across MCS-certified contractor quotations and published UK market data in August 2026, cross-checked against DESNZ cost-per-kW reporting for MCS-registered domestic installations. Generation figures use the MCS MIS 3002 Kk methodology at a Kk of 900 for a south-west facing Midlands roof at 35 degrees with no shading. Financial figures use the Ofgem price cap electricity unit rate of 26.32p/kWh for 1 October to 31 December 2026 and a 12p/kWh export rate.

DISCLAIMER: All prices are indicative and vary by region, roof covering, access, scaffolding requirement and installer. We do not provide financial advice. The Smart Export Guarantee is administered by Ofgem, with rates set by individual suppliers, so confirm the live rate before applying. Consumption bands by property type are drawn from industry consensus and Ofgem typical consumption values; no government dataset maps bedroom count directly to annual kWh.

UPDATED: August 2026. Reflects the Ofgem price cap for 1 October to 31 December 2026 announced on 26 August 2026, the reduction of Outgoing Octopus from 15p to 12p on 1 March 2026, and the 0% VAT window on qualifying installations through to 31 March 2027.