Solar 101 / Installation

The exciting time from getting quotes, to switch on day.

If you’re just getting quotes, or you’ve paid a deposit and booked your install, you probably want to know what the process will look like. Most of the time is spent on picking your installer, waiting for paperwork and then a few noisy days on the roof.

Let’s see what the whole process looks like.

Key Points
  1. The install is quicker than the run-up to it. Panels go on in one to three days, but the survey, design, scaffolding and grid paperwork stretch the full journey to four to ten weeks.
  2. Panels clamp to rails, not to your roof. Installers lift tiles, bolt roof hooks into the rafters, fit rails, then clip the panels to the rails. Done properly, no tiles are damaged.
  3. The electrics are the part that needs certifying. A qualified electrician wires the DC and AC sides, and the job must be certified under MCS (or Flexi-Orb) and notified to your network operator.
  4. Grid connection has a threshold. Systems up to 3.68kW per phase are notified after the fact (G98). Bigger ones need advance approval from your Distribution Network Operator (G99).
  5. Certification unlocks the payments. Without an MCS certificate you can’t claim a Smart Export Guarantee tariff, which is the main reason DIY installs rarely make financial sense.
This animation needs JavaScript to play.
0:00 / 1:54

The short version

A rooftop install on a UK home follows the same shape whoever does it. You get a survey, the installer designs a system and quotes for it, scaffolding goes up, a small team spends one to three days fitting the mounting, panels, inverter and any battery, an electrician wires and tests the lot, and the system is commissioned and registered with your network operator. After that you sign up to an export tariff so you get paid for the electricity you send back to the grid.

The order rarely changes. What varies is the timeline, the roof-mounting method and the amount of electrical work, which is where the cost and quality differences show up.

Enquiry to switch-on: the typical timeline
Week 1
Enquiry, remote survey and quote

You share photos or hop on a video call. The installer assesses the roof, sizes the system and sends a design and price.

Weeks 2-4
Design sign-off and grid application

You approve the design. If the system needs advance grid approval, the installer files it now. Kit is ordered.

Days before
Scaffolding goes up

Usually four or five days ahead, so the roof team can work safely.

Install
One to three days on site

Mounting, panels, inverter, battery, wiring, testing and commissioning. This is the part people mean by “installation”.

Weeks after
Certificate, export tariff and scaffold down

Your MCS certificate arrives, you register for an export tariff, and the scaffolding comes down once everyone is happy.

Before anyone climbs on the roof

Get the run-up right and the roof work is almost boring, which is exactly what you want.

Checking whether you need planning permission

Most rooftop installs in the UK fall under permitted development, which means no planning application. The common exceptions are listed buildings, streets where the council has withdrawn those rights (an Article 4 direction), larger ground-mounted arrays and, in conservation areas, panels on a wall facing a highway. A decent installer checks this at the quoting stage rather than leaving you to find out. If your home is affected, allow an extra eight to twelve weeks for the council to decide.

The survey and system design

The survey is where the installer works out what your roof can take: its condition, pitch, orientation and shading, and whether there’s enough clear space. Most of this is now done remotely from photos or a video call, which is just as thorough for a straightforward roof. Hipped, vaulted and flat roofs usually still get an in-person structural check.

Orientation and angle drive how much you’ll generate. South-facing is the classic choice, though an east-west split can fit more panels and spread output across the day. It’s worth reading up on the best roof angle before you sign off a design, so you can ask sensible questions. The installer then sizes the array to your electricity use and roof space, and picks the hardware to match.

Two design choices matter here. First, the inverter, which converts the panels’ DC electricity into the AC your home uses; many 2026 installs use a hybrid inverter so a battery can be added later without swapping it out. Second, shade. If a chimney, tree or dormer shades part of the array, one shaded panel can drag down a whole string on a basic setup, so the design should include microinverters or power optimisers, which let each panel work independently.

Tip

Ask to see the shading analysis and the panel layout drawing before you approve the design. A reputable installer produces both. If a quote arrives with only a system size and a price, you’re being asked to buy blind.

The installation, hour by hour

Once the design is approved and any grid application is in, here’s the sequence a team works through.

01
Scaffolding and safe access

The scaffold lets the team carry panels and mounting gear up safely, and takes only a few hours to put up. Good installers leave it up for a week or two afterwards, so any snag can be fixed without paying to re-erect it.

02
Fitting the mounting system

Tiles are lifted, roof hooks are bolted to the rafters, and the tiles go back. Aluminium rails are then fixed to the hooks. This frame carries the whole array and is the single most important part for long-term security.

03
Mounting the panels

Panels are lifted up, positioned and clamped to the rails, then linked with pre-fitted DC connectors. If you’ve opted for bird proofing, mesh is fitted around the array edge at this stage.

04
Installing the inverter and battery

The inverter, and battery if you have one, go somewhere cool and well ventilated: a garage, utility space or a protected outside wall, mounted a metre or two apart. PAS 63100 guidance keeps batteries out of bedrooms and escape routes, and discourages lofts.

05
Running the cables

A DC cable carries power from the roof to the inverter, an AC cable takes the converted power to a small dedicated fuse board, and a comms cable links the system to your meter. Cables are hidden in trunking or fed through existing routes to keep them tidy.

06
Connecting to your consumer unit

The electrician ties the system into your fuse box. This is the point where the power is switched off, usually for around an hour.

07
Testing and commissioning

Every connection is checked, the system is energised, and the monitoring app is set up on your phone. The team spends ten minutes showing you how to read your generation and, if you have a battery, how it charges and discharges.

Did you know

A finished 12-panel system weighs roughly 240kg spread across the whole roof, about 10kg per square metre. That’s well within what a standard UK pitched roof carries, which is why most homes need no structural strengthening.

How panels attach to your roof

This is the part homeowners worry about most, so it’s worth being specific. Panels are never screwed straight through your tiles. The load path runs from the panel into the clamp, into the rail, into a roof hook, and finally into the timber rafter underneath. The tiles simply sit back over the hooks.

On-roof versus in-roof

Most installs are on-roof: the panels sit a few centimetres above your existing tiles on rails. It’s quicker, cheaper and easy to service. In-roof (or integrated) mounting removes the tiles under the array and sets the panels flush into the roof surface, which looks neater and suits new builds. It costs more and needs careful flashing to stay watertight, so it’s a choice to weigh up rather than a default.

Tiles, slate and watertightness

Standard concrete or clay tiles lift easily to seat a roof hook. Slate is more brittle and often can’t rest on a hook without cracking, so the installer cuts a small recess or uses a slate-specific bracket, then beds everything back down. Cables pass through the felt membrane under your tiles between overlapping sections, so nothing is torn. Understanding how the panels stay fixed makes it easier to judge whether a team is being careful.

Warning

A properly fitted array shouldn’t cause roof leaks. Almost every leak traced to solar comes from a rushed penetration or a cracked tile left unsealed, and any tile damaged during the work should be repaired before the team leaves.

Testing, sign-off and grid connection

The system isn’t finished until it has been tested, certified and registered with your electricity network. This is the paperwork that protects you and gets you paid.

MCS certification

A domestic install should be certified under the Microgeneration Certification Scheme, or the equivalent Flexi-Orb scheme. The certificate confirms the work meets the standard and is what suppliers ask for before they’ll put you on an export tariff. The electrical work also has to comply with the wiring and building regulations that cover electrical work in the home.

G98, G99 and your network operator

Every grid-connected system has to be declared to your Distribution Network Operator, the company that runs the local cables, and the route depends on size. An inverter rated up to 3.68kW per phase falls under G98, a simple notification sent within 28 days of switch-on. Anything larger needs a G99 application, submitted and approved before connection, so the operator can check the local network can absorb your exports. A good installer handles the whole DNO application for you. Fast-tracked domestic applications come back in around ten working days, though a standard G99 application gives the operator up to 45 working days.

The physical roof work is the bit people photograph. The certification and grid sign-off is the bit that actually turns your panels into a paying asset. Solar Love Editorial // Installation desk

What the installation actually costs

Headline system prices bundle everything together, which hides how much of your money goes on the install rather than the kit. For a typical 4kW system in 2026, panels and inverter are only a little over half the bill; mounting, scaffolding, labour and certification make up the rest. Here’s a realistic breakdown for a standard two-storey home with panels and a hybrid inverter, no battery.

Typical 4kW install, panels + inverter, UK 2026 Total £6,500
Solar panels (10 x 410W)
Tier-1 monocrystalline, 25-year performance warranty
£2,600
Hybrid inverter
Battery-ready, 10-year warranty
£900
Mounting, rails and cabling
Roof hooks, aluminium rails, DC and AC cable, isolators
£700
Scaffolding
Standard two-storey, single elevation
£1,000
Labour
Two installers, roughly 1.5 days on site
£900
Certification and admin
MCS certificate, DNO notification, commissioning, monitoring setup
£400

Add a 10kWh battery and the total typically lands between £9,500 and £12,000, since the battery is the single biggest line item. For a fuller picture of hardware pricing and system sizes, see our guide to what solar panels cost. Two things push the number up more than most people expect: the roof and the region.

What pushes installation labour up (relative effort)
Simple south-facing tiled roof Baseline
Slate or fragile tiles + time
Multiple roof faces / hips + time
Three storeys / hard access + scaffold

Where you live matters too. Installer labour rates in London and the South East run well above those in the North East, Yorkshire or Wales, so an identical system can vary by a thousand pounds or more across regions. Three quotes on the same specification is the only way to know you’re paying a fair rate.

After the switch-on

Once the system is live, two jobs remain, and one of them pays you.

Registering for an export tariff

With your MCS certificate in hand, you can sign up to a Smart Export Guarantee tariff and get paid for surplus electricity you send to the grid. Your chosen supplier asks your network operator for an export meter number, which takes one to four weeks, after which you submit a reading and payments begin. Rates vary widely between suppliers, so compare before you commit.

Monitoring and maintenance

Solar needs little upkeep, but it isn’t fit-and-forget. The monitoring app is your early-warning system: a panel or string producing far less than its neighbours points to a fault worth investigating. An occasional visual check from the ground after big storms, and a clean every few years if your panels are shallow-pitched or under trees, is about the extent of it.

Tip

Check your monitoring app monthly for the first year. It teaches you what a normal day looks like for your roof, so anything abnormal later stands out immediately.

Flat roofs, ground mounts and barns

The process shifts when the location changes.

On a flat roof, drilling is usually avoided to protect the waterproof layer, so panels sit on a ballasted frame weighted down against wind. That adds a lot of weight, around 80kg per panel, which is why flat-roof arrays are more common on commercial buildings with strong decks. Panels are also tilted and spaced so they don’t shade each other, which limits how many fit.

A ground-mounted array skips scaffolding but needs a proper foundation, either concrete footings or driven posts, plus a mounting frame. Beyond a few panels it needs planning permission, and more open, unshaded land than most households have. Barns and outbuildings can work well if the roof is sound and the inverter sits inside, keeping cable runs short.

Can you install solar panels yourself?

You can buy the parts, but a full DIY install is a poor idea for most people, and not mainly because of the roof work. The electrical connection must be done by a qualified person and certified, and a self-installed system is very unlikely to gain MCS or Flexi-Orb certification. Without that certificate you can’t claim an export tariff, which removes a large chunk of the financial case, and you forgo the workmanship warranty and paperwork an insurer or future buyer will ask for. Add the risk of working at height with live DC cabling, and the sums rarely favour going it alone.

How to prepare, and red flags to watch

You don’t need to do much before install day, but a little preparation keeps things smooth.

  • Clear access to your loft, fuse box and meter. The team will need clean routes between them.
  • Move cars off the drive. Scaffolders and the delivery van need the space.
  • Have your wifi password ready. The system connects to the internet during commissioning.
  • Be home for the start of day one. You’ll agree the cable route and battery location in person.
  • Save the paperwork somewhere findable. The MCS certificate and design drawings matter when you sell or claim.

Just as useful is knowing what a good and a bad job look like from the ground.

Signs of a good install

Cables run neatly in trunking, not draped across the roof.

You’re shown photos of the mounting points and given a roof condition report.

The MCS certificate and DNO notification arrive without chasing.

Red flags

A deposit of more than about a quarter of the price demanded up front.

Scaffolding or certification quoted as optional extras.

Pressure to sign on the day with a discount that expires by midnight.

Important

Know your consumer rights before you sign. Under the redeveloped MCS scheme, installers must give you the MCS Customer Commitment, which covers deposits, cancellation and dispute resolution, and buy an MCS-approved financial protection product for your job. Many also belong to a consumer code such as RECC or HIES, which adds an independent route to complain if something goes wrong.

Terms used in this guide
Roof hook
A metal bracket bolted to a rafter that anchors the mounting rails. The panels’ entire weight ends up here.
String
A chain of panels wired in series. On a basic setup, the weakest panel in a string limits the rest, which is why shading matters.
Inverter
The box that converts the panels’ DC electricity into the AC your home and the grid use. A hybrid inverter also manages a battery.
Commissioning
The final testing and activation stage, where the system is energised, checked and connected to monitoring.
DNO
Distribution Network Operator, the company running your local electricity cables. It must be told about any grid-connected system.
MCS
The Microgeneration Certification Scheme. Its certificate proves the install meets the standard and is needed to claim an export tariff.
Frequently asked
How long does it take to install solar panels?

The roof work takes one to three days for most homes, with larger or more complex roofs adding a day or two. The full journey from enquiry to switch-on, including survey, scaffolding and grid paperwork, usually runs four to ten weeks.

Will my power be off during the installation?

Only briefly. The electrician switches the power off for about an hour to connect the system to your fuse box safely. For the rest of the job you keep normal power.

Do installers damage the roof when fitting panels?

They shouldn’t. Tiles are lifted to bolt roof hooks into the rafters, then replaced. The only common exception is brittle slate, which may need a small recess cut or a specialist bracket. Any tile broken during the work should be repaired before the team leaves.

Do I need scaffolding to install solar panels?

For a pitched roof, yes. Scaffolding lets the team carry heavy panels and mounting gear up safely. Flat-roof and ground-mounted systems can often be installed without it.

Does the installation include the battery?

Only if you order one. A battery is a separate line item, and the biggest single cost in a solar-plus-storage system. If your inverter is a hybrid, you can add storage later without replacing it.

Can I use the panels immediately after install?

The system generates from the moment it’s commissioned. To get paid for exported electricity, though, you need your MCS certificate and an export tariff, which is arranged in the weeks after the install.

Bottom line

The roof work is the easy part

Survey, design, scaffold, mount, wire, test, certify, connect. The fitting takes one to three days, but the survey, grid application and certification stretch the full journey to a couple of months, and that back-office work is what unlocks the export payments.

The differences between installers rarely show up on the roof. They show up in the mounting detail, the neatness of the wiring, the roof condition report, and whether the certificate and DNO notification land without chasing. Get three quotes on a like-for-like specification, check for MCS certification, and treat a pushy deposit demand as your cue to walk away.

METHODOLOGY: Cost figures reflect UK market averages for MCS-certified residential installs in 2026, cross-checked against DESNZ solar PV cost data and installer and comparison sources. The 4kW breakdown is illustrative for a standard two-storey, single-elevation tiled roof; your quote will vary by roof type, region and hardware.

DISCLAIMER: All prices are indicative and exclude site-specific factors. This guide is general information, not financial or structural advice. Always use an MCS-certified or Flexi-Orb-certified installer and confirm details against your own quote and survey.

UPDATED: 20 October 2026. Reflects the 0% VAT window on energy-saving materials through 31 March 2027.