Before your solar panels can legally export electricity to the grid, your Distribution Network Operator (DNO) needs to know about them. This is not optional – it is a legal requirement. The good news is that for most residential installations, the process is straightforward and handled entirely by your installer.

The DNO application ensures the local electricity network can safely handle your system export. In areas with lots of solar already installed, the grid may have constraints that affect what you can connect or how much you can export. Understanding this process helps you know what to expect and avoid surprises.

This guide explains what DNO applications involve in practice, how to work out which type applies to your system (including with batteries), what can go wrong, and what to ask your installer to ensure the process goes smoothly.

DNO Applications at a Glance

What it isNotification/application to connect generation to the grid
Why requiredLegal requirement; ensures grid safety and stability
Who appliesYour installer (on your behalf)
G98 (small systems)Notification only; no approval needed before install
G99 (larger systems)Full application; approval required before install
CostUsually free; included in installation
Timeline (G98)Notification within 28 days of commissioning
Timeline (G99)Apply before install; 45-90+ working days

For the broader regulatory context – what DNOs actually do, what they assess during a G99 application, and the escalation routes if things go wrong – see our companion DNO approval process guide. This article focuses on the practical application side: working out which type applies to your system and getting the paperwork right.

What Is a DNO?

Distribution Network Operators

What they doOwn and operate local electricity distribution networks
Their networkCables, substations, transformers in your area
Not the same asYour energy supplier (who you pay bills to)
ResponsibilityGetting electricity from transmission grid to your home

UK DNOs by Region

DNOAreas Covered
UK Power Networks (UKPN)London, South East, East of England
Western Power Distribution (National Grid)Midlands, South West, Wales
Electricity North WestNorth West England
Northern PowergridNorth East England, Yorkshire
Scottish Power Energy NetworksCentral/Southern Scotland, North Wales, Merseyside
Scottish and Southern Electricity Networks (SSEN)Northern Scotland, Central Southern England

G98 and G99 are Engineering Recommendations from the Energy Networks Association’s generation connection guidance – the industry standards each DNO works to. The forms themselves are standardised across all six DNOs, but each operator runs its own portal and has its own processing quirks.

G98 vs G99: Which Applies to You?

G98 – Small-Scale Generation

Applies toMost residential solar installations
Single phase limitUp to 3.68 kW inverter capacity per MPPT
Three phase limitUp to 11.04 kW (3.68 kW per phase)
ProcessNotification only – no pre-approval needed
TimingNotify DNO within 28 days of commissioning

G99 – Larger Generation

Applies toSystems exceeding G98 limits
ThresholdAbove 3.68 kW single phase / 11.04 kW three phase
ProcessFull application required before installation
Approval requiredYes – cannot install until approved
Timeline45-90+ working days

Quick Reference: Which Do I Need?

System SizeSupply TypeApplication Type
Up to 3.68 kW inverterSingle phaseG98 notification
Up to 11.04 kW inverterThree phaseG98 notification
3.69-50 kW inverterSingle phaseG99 application
11.05-50 kW inverterThree phaseG99 application
Above 50 kWAnyG99 full application

The G98 Notification Process

What Happens

StepWhoWhat
1InstallerInstalls and commissions system
2InstallerCompletes G98 notification form
3InstallerSubmits to DNO within 28 days
4DNOAcknowledges and records installation

G98 Notification Information

Information RequiredDetails
Customer detailsName, address, MPAN (meter number)
System detailsInverter make, model, capacity
Panel detailsTotal capacity, number of panels
Commissioning dateWhen system was activated
Installer detailsCompany, MCS certification number

G98 Timeline

EventTiming
InstallationCan proceed without waiting
CommissioningSystem activated
Notification deadlineWithin 28 days of commissioning
DNO acknowledgementUsually within a few weeks

The G99 Application Process

G99 Application Steps

StepWhoWhatTimeline
1InstallerComplete G99 application formBefore install
2InstallerSubmit to DNO with technical detailsDay 0
3DNOAcknowledge receipt~5 working days
4DNOAssess application; network studiesVaries
5DNOIssue connection offer45-90+ working days
6CustomerAccept offer; pay any charges
7InstallerInstall systemAfter approval

G99 Timelines

Application TypeTarget Timeline
G99 A1/A2 (under 50 kW)45 working days
G99 B (50 kW – 1 MW)65 working days
G99 C (above 1 MW)90 working days
RealityOften longer; constrained areas much longer

Grid Constraints and Export Limits

What Are Grid Constraints?

DefinitionLocal network cannot accept more generation
CauseHigh solar uptake; transformer/cable limits
Affected areasRural areas; affluent suburbs; anywhere with lots of solar
Increasing problemMore common as solar deployment grows

Types of Constraints

ConstraintDescription
Voltage riseExport pushes local voltage too high
Thermal limitsCables/transformers cannot handle more power
Reverse power flowSubstation equipment cannot handle export
Fault levelGeneration increases fault current beyond limits

What Happens in Constrained Areas

OutcomeWhat It Means
Zero export limitSystem cannot export at all
Reduced export limitCan export less than inverter capacity
Timed exportExport limited during peak solar hours
Flexible connectionExport curtailed when network constrained
Required upgradesMust pay for network reinforcement

Export Limiting

What it isInverter limited to export less than capacity
How it worksInverter programmed with export limit
Example5 kW inverter limited to 3.68 kW export
Self-consumptionCan still use full capacity for home use
Common solutionAllows larger systems under G98

Export limiting has gone from a niche workaround to the most common way to install a 5-6 kW inverter on a typical UK home. For the technical detail on how it actually works at the inverter level, what happens to the surplus, and which inverters do it well, see our export limitation guide.

Zero Export

What it isSystem cannot export any power to grid
How it worksInverter monitors and prevents export
Excess powerCurtailed (wasted) or stored in battery
When requiredSeverely constrained networks
ImpactNo SEG payments; reduced financial benefit

Batteries and DNO Applications

Do Batteries Need DNO Notification?

Battery-only systemMay need notification if can export
Solar + batteryCombined inverter capacity counts
AC-coupled batteryHas own inverter; adds to total
DC-coupled batteryShares solar inverter; no additional capacity
Hybrid inverterSingle inverter handles both; counts once

This is the area that catches most homeowners by surprise. Understanding the difference between AC and DC coupling matters more for the DNO application than for any other reason – see our breakdown on AC vs DC coupled batteries for the technical detail.

Examples

SystemTotal CapacityApplication Type
3.6 kW solar + DC-coupled battery3.6 kW (shared inverter)G98
3.6 kW solar + 5 kW AC battery8.6 kW totalG99 (single phase)
5 kW hybrid inverter5 kWG99 (single phase)
3.68 kW solar + 3.68 kW battery7.36 kWG99 (single phase)

If you’re retrofitting a battery to existing solar, the same combined-capacity rule applies. A homeowner with a G98-registered 3.68 kW solar system who adds an AC-coupled battery with its own 5 kW inverter has just pushed the combined site capacity to G99 territory and triggered a fresh DNO application.

Common Issues and Solutions

Application Rejected

ReasonSolution
Incomplete applicationProvide missing information
Technical errorsCorrect and resubmit
Grid constraintsAccept export limit or wait for upgrade
Non-compliant equipmentUse compliant inverter

Export Limitation Imposed

OptionConsideration
Accept limitStill worthwhile if mainly self-consuming
Add batteryStore what you cannot export
Reduce system sizeMay get full export for smaller system
Pay for upgradeRarely economical for residential

What Your Installer Should Handle

Installer Responsibilities

TaskInstaller Role
Determine application typeG98 or G99 based on system size
Complete formsFill in all technical details
Submit applicationSend to correct DNO
Chase progressFollow up on G99 applications
Configure export limitsProgram inverter if required
Provide documentationGive you copy of notification/approval

Questions to Ask Your Installer

QuestionWhy It Matters
Is this G98 or G99?Affects timeline and process
Are there known constraints in my area?May affect export capability
Will you handle the DNO application?Should be included
When will notification be submitted?Should be within 28 days
Will I get a copy of the notification?Important for your records

If you’re checking whether a quote properly includes DNO application work and is otherwise complete and competitive, our solar panel quote checker walks through the line items a compliant quote should always show.

Costs

G98 Costs

DNO notification feeFree
Installer adminIncluded in installation cost
Total cost to you£0 (included)

G99 Costs

Cost TypeTypical Amount
Application feeOften free for small G99
Connection feeVariable; depends on work needed
Network reinforcementCan be substantial if required
Installer adminMay charge extra for G99 handling

Future System Changes

When You’ll Need Another Application

ChangeDNO Implication
Add panels (same inverter)Notify DNO; usually no fresh application
Add panels (more inverter capacity)Fresh G98 or G99 depending on new total
Add AC-coupled batteryLikely G99; combined capacity rule
Replace inverter (same size)Notification; DNO needs updated equipment data
Replace inverter (larger size)Fresh application if it crosses 3.68 kW

If you’re considering adding more panels to your existing system later, plan the inverter capacity now. An installer can spec a 5 kW inverter on day one with export limited to 3.68 kW, which gives you headroom to add panels later without triggering a fresh DNO application.

After Approval and SEG

Linking DNO Approval to Export Payments

StepWhat Happens
DNO acknowledgesSystem recorded on grid database
MCS certificate issuedRequired for SEG eligibility
Apply for SEGWith your chosen energy supplier
Smart meter installedRequired to measure export
Export payments beginPer-kWh tariff for what you export

If you’re trying to estimate what your export payments might look like once you’ve signed up to SEG with a supplier, our SEG calculator works through typical UK system sizes and current tariff rates.

Summary

AspectKey Points
G98Up to 3.68 kW single phase; notification only; no pre-approval
G99Above G98 limits; full application; approval before install
Who handles itYour installer should do everything
CostUsually free and included
Timeline (G98)Notify within 28 days; no wait
Timeline (G99)45-90+ working days; wait for approval
Grid constraintsMay limit export; increasingly common
Keep documentationImportant for SEG registration and records

For most UK residential solar installations, the DNO process is invisible – your installer handles everything, and you do not need to wait for approval. As long as your system stays within G98 limits (3.68 kW inverter on single phase), it is a simple notification submitted after installation.

If you are planning a larger system, battery storage with significant inverter capacity, or live in an area with grid constraints, the process becomes more complex. G99 applications take time and may result in export limitations. Understanding this upfront helps you plan realistically and avoid disappointment.

The key takeaway: make sure your installer includes DNO notification in their service, get a copy of the submitted notification for your records, and ask about any known grid constraints in your area before committing to a system size. If you are told there are constraints, discuss how this affects your options – a battery may make sense if export is limited.

Three things to nail down before you sign. First, get the application type in writing – your quote should explicitly say “G98 notification” or “G99 application”, and if it’s G99, the timeline impact on your install date should be acknowledged. Second, ask about constraints by postcode – any installer worth using in your area will have experience of recent jobs nearby and will know if the local feeder is full. Third, plan inverter capacity around future plans – if there’s any chance you’ll add a battery or more panels later, oversizing the inverter now (with export limiting) saves you a fresh G99 application down the line.

Once you’re up and running, keep three documents safe: the DNO acknowledgement or connection offer, the MCS certificate, and the commissioning paperwork. You’ll need all three when applying for SEG payments and when selling the property.